Into the Final Lap

Building Commissioner Josh Morse has been posting some fantastic pictures of the pool construction and shared them with us for posting here.

The pool remains on schedule, with an opening date scheduled for June and the upcoming timeline here:

5/20 – Pool tile, waterline install, pool deck pours, ramps & stairs

5/28 – Pool plaster, spray deck plumbing, pool deck pours

6/3 – Fill and treat pools, waterslide & DB install, spray deck pad, pool deck pours, fence install.

6/10 – Training, shade structures, landscaping, splash pad curing

6/17 – Shade structures, splash pad curing

6/24 – Splash pad rubberized surface install

7/1 – Install splash pad spray features